Concrete calculator
Estimate concrete volume and bags for slabs, footings and columns.
- Net volume
- 1.2 m³
- Order volume (with waste)
- 1.32 m³
- Cubic yards (with waste)
- 1.72649 yd³
- 80 lb bags (0.6 ft³ each)
- 78 bags
- 60 lb bags (0.45 ft³ each)
- 104 bags
Formula
Slab: V = L × W × T. Column: V = π × D² / 4 × H. Order = V × quantity × (1 + waste %)Dimensions are converted to metres. Bags = order volume in ft³ divided by the bag's yield, rounded up.
Diagram
How it is calculated
- Convert all dimensions to metres.
- Slab or footing: V = L × W × T. Round column: V = π × D² / 4 × H.
- Multiply by the quantity, then by (1 + waste %) for the order volume.
- Convert to cubic yards (× 1.30795) and divide by each bag's yield to count bags, rounding up.
Always compare the bag yield on your product label, because brands differ.
Worked examples
A patio slab
4 m × 3 m, 10 cm thick, 10% waste. Result: Net volume: 1.2 m³; Order volume (with waste): 1.32 m³; Cubic yards (with waste): 1.72649 yd³; 80 lb bags (0.6 ft³ each): 78 bags.
Four round piers
Four columns, 0.4 m across and 3 m high, 10% waste. Result: Net volume: 1.50796 m³; Order volume (with waste): 1.65876 m³; 80 lb bags (0.6 ft³ each): 98 bags.
In feet and inches
A 10 ft × 10 ft slab, 4 in thick, 5% waste. Result: Order volume (with waste): 0.99109 m³; Cubic yards (with waste): 1.2963 yd³; 80 lb bags (0.6 ft³ each): 59 bags.
Key terms
- Slab
- A flat concrete layer such as a floor, pad or patio.
- Footing
- A concrete base that spreads a load into the ground.
- Waste allowance
- Extra concrete ordered to cover spillage, uneven ground and over-excavation.
- Cubic yard
- A volume unit used for ready-mix in North America. 1 yd³ is about 0.7646 m³.
- Yield
- The volume of wet concrete one bag makes. 80 lb bags commonly yield about 0.6 ft³.
- Ready-mix
- Concrete delivered wet by truck. It is usually cheaper than bags above a small volume.
Assumptions and limits
Bag yields vary by product, so use the figure on your bag. Allow for uneven subgrade, formwork deflection and spillage, and ask your supplier for ready-mix minimums. Structural design needs an engineer. See the disclaimer.
How much waste should I add?
A small allowance is common, often 5 to 10%, but uneven ground and complex forms need more. Ask your supplier.