How to Estimate Concrete for a Slab or Footing
Last reviewed 2026-10-12
Estimating concrete means calculating the volume, adding an allowance for waste, then converting to bags or a ready-mix order.
Calculate the volume
For a slab or footing, multiply length, width and thickness in the same unit. A 4 m × 3 m slab that is 10 cm thick is 1.2 m³. A round column uses π × D² / 4 × height.
Add a waste allowance
Spillage, uneven ground and slightly deep excavation use extra concrete. A small allowance is common, but complicated jobs need more. Ask your supplier what they recommend.
Bags or ready-mix
Bag yield is printed on the bag, and brands differ. For example, about 78 bags of 80 lb mix make 1.32 m³. Above a small volume, ready-mix is usually easier and cheaper.
Before you pour
Check the formwork, subgrade and any reinforcement. Structural designs need an engineer, and local codes set minimum thicknesses and strengths.